NERPSIP Scheme: The Scheme was initially approved in 2014 as a Central Sector Plan Scheme of the Ministry of Power.
-
Funding: The scheme is being funded with the assistance of the World Bank fund and by the Government of India through the Budget support of the Ministry of Power on a 50:50 basis.
-
Objective: Government’s commitment for the total economic development of the North Eastern Region and to strengthen the Intra-State Transmission & Distribution Infrastructure in the North East Region.
-
Implementation: The scheme is being implemented through Power Grid Corporation of India Limited (POWERGRID).
-
Beneficiary States: Assam, Manipur, Meghalaya, Mizoram, Nagaland, and Tripura and is targeted to be commissioned by December 2021.
-
Recently, Cabinet approved revised cost estimate of NERPSIP.
-
It will create a reliable power grid and improve NER States’ connectivity to the upcoming load centers.